Firm Capacities

Capacity tariffs for bookings of firm entry and exit capacities for a booking period of one year:
FZK
3
3200
€/(kWh/h)/a
DZK to DZK5
2
9880
€/(kWh/h)/a

Interruptible capacities

Interruptible capacities

The discount for interruptible capacities, in accordance with the Bundesnetzagentur-decision BK9-19/612, dated 27 May 2020, is 10% of the tariff of the firm freely allocable capacity (FZK)
The exceptions to this are the following combinations of point and duration, for which the discount is 11% of the tariff of the firm freely allocable capacity (FZK):

- Exit point Achim II: all durations
- Exit point Deutschneudorf: Quarter, Month, Day and Within Day
- Entry points Greifswald and Lubmin II: Day and Within Day

Tariff for interruptible capacities with 10% discount
2
9880
€/(kWh/h)/a
Tariff for interruptible capacities with 11% discount
2
9548
€/(kWh/h)/a

Capacities with durations of less than one year

For bookings of capacities with durations of less than one year (capacity products with durations of less than one year mean Quarter, Month, Day as well as Within-Day) the following multipliers, in accordance with the MARGIT-decision BK9-18/612, apply:
Quarter
1
10
Month
1
25
Day
1
40
Within-Day
2
00