Incremental Capacity
Incremental Process - Overview
Incremental processes concern market-based network capacity expansion projects: additional capacity at existing Interconnection Points or the creation of new Interconnection Points, in both cases realized through investments that are underpinned by market commitments. The incremental process (INC) is complementary to network development planning (ENTSOG TYNDP, GRIPs or the Fluxys Investment Plan), as it adds the market perspective concerning readiness to commit on a long term basis to trigger the realisation of specific infrastructure.
In accordance with Commission regulation (EU) 2017/459, adjacent TSOs on each side of Interconnection Points linking entry-exit zones will cooperate during the incremental process. The incremental process is started at least every two years, during odd numbered years, but can also be started in even numbered years. The incremental process is kicked-off by the yearly auctions, which are held in July of each year. The incremental process consists of the following phases:
- Non-binding demand indications, that can be submitted at any time.
- Market demand assessment report (DAR), that will conclude whether the conditions are met to envisage the next steps (and therefore a potential network expansion).
- Design phase, including market consultation and national regulatory agency (NRA) approval of the project(s).
- Publication of the binding project notice.
- Binding allocation of incremental capacity, whereby binding bids for capacity are eventually awarded, before a final investment decision (FID) is taken on the necessary investments.
For the assessment of incremental (or new) projects not in the scope of CAM NC, the open season procedure remains applicable.
Incremental process 2025
The following diagram illustrates the key dates of the incremental process
7 July 2025 |
1 September 2025 |
27 October 2025 |
|||
Yearly
|
Deadline submission of non-binding Start of work on DAR 2025
|
Publication of DAR - On Fluxys website
(16 weeks after Yearly Capacity Auction start)
|
|||
![]() |
![]() |
![]() |
![]() |
![]() |
Step 1 – Non-binding demand indications
Parties interested in incremental capacity can submit non-binding demand indications at any time. However in the 2025 market demand assessment, Fluxys considered non-binding demand indications submitted no later than 1 September 2025 (cob). Non-binding demand indications received after this deadline will be considered in the next market demand assessment – in 2027.
Non-binding demand indications can be submitted using the non-binding demand indications templates:
Fluxys Belgium
Download this form and send it to info.transport@fluxys.com.
Fluxys TENP & Deutschland
Download this form and send it to the TSO association FNB Gas.
Interconnector
Download this form and send it to consultation@interconnector.com.
Step 2 – Demand Assessment Reports (DAR)
Fluxys Company |
IPs/Market Areas | TSOs | Document | |
---|---|---|---|---|
Fluxys Belgium | ZTP-TTF | Fluxys Belgium / GTS | Published when available | |
Fluxys Belgium | ZTP-PEG | Fluxys Belgium / NaTran | Published when available | |
Fluxys Belgium | ZTP-THE |
Fluxys Belgium / Fluxys TENP, Gascade, OGE, Thyssengas, Creos |
Published when available | |
Fluxys Belgium | ZTP-IZT | Fluxys Belgium / Interconnector |
Published when available | |
Fluxys Deutschland |
THE-RU | Fluxys Deutschland, GASCADE, Gasunie Deutschland, NEL Gastransport, ONTRAS Gastransport, OPAL Gastransport | Published when available | |
Fluxys Deutschland |
THE-N4G | Fluxys Deutschland, GASCADE, ONTRAS Gastransport, Gasunie Deutschland, NaTran Deutschland, OGE / NET4gas |
Published when available |
|
Fluxys TENP | THE-ZTP | Fluxys TENP, GASCADE, OGE, Thyssengas, Creos / Fluxys Belgium |
Published when available | |
Fluxys TENP | THE-Switzerland | Fluxys TENP, Terranets BW, OGE |
Published when available | |
Fluxys TENP | THE-TTF | Fluxys TENP, GASCADE, Gasunie Deutschland, Thyssengas, Gastransport Nord, OGE / GTS |
Published when available | |
Interconnector | IZT-ZTP | Interconnector / Fluxys Belgium | Published when available | |
Interconnector | IBT-NGG | Interconnector / National Gas Transmission | Published when available |
Once the Demand Assessment reports are available you can also consult these on the ENTSOG website.