Pipeline Zeebrugge - Evergem

Why this infrastructure?

This project forms the second phase of the overarching Zeebrugge–Opwijk pipeline project. Find out more about the first phase: the Desteldonk–Opwijk project.

Fluxys is a key pioneer in the energy transition in Belgium. Partly because of the war in Ukraine, Europe wants to transition rapidly to sources other than Russian natural gas. That's why Fluxys is preparing for the construction of a pipeline between Zeebrugge and Evergem. The missing link in the Belgian gas network is a future-oriented solution to ensure that there is a continuous energy supply to Belgium and neighbouring countries.

Building this pipeline is also an important step in implementing Belgium's federal hydrogen strategy and the Flemish hydrogen vision (or Flemish hydrogen policy strategy), which aim to make our country a European hydrogen hub. We are constructing this pipeline to be ready for carrying the molecules of the future. This means that we can eventually switch it over to hydrogen so that suppliers can get this carbon-neutral energy carrier onto the market. Find out more about how we are building hydrogen and CO₂ infrastructure for Belgium.

We will start work on constructing this strategic pipeline as soon as the necessary permits have been issued. According to the current schedule, work could begin in 2025.


Facts and figures

  • The pipeline will run through Zeebrugge, Bruges, Knokke–Heist, Damme, Maldegem, Lievegem and Evergem.
  • Length of Zeebrugge–Evergem pipeline: 53 km
  • Diameter: 1,000 mm

Consultation

Landowners and operators have their own point of contact at Fluxys, from the preliminary study phase of the project through to the restoration of the site following the construction of the pipeline. This allows them to consult with someone familiar with their concerns and the features of their land from the outset.

When? With whom? On what?
From February 2023
Landowners and operators Identification of and initial contact with the parties concerned
From September 2023 Landowners and operators Information sessions presenting the project – the local residents concerned receive a personal invitation
After the start of the Declaration of Public Utility procedure (December 2023/January 2024) Landowners Conclusion of easement agreements with the owners of land crossed by the pipeline
Before opening up the working strip (early 2025) Operators Production of a joint site description
Once the trench has been dug Operators Description of presence and condition of drainage
After the restoration of drainage Operators Confirmation of restoration of the drainage
After the restoration of the site(s) Operators Site acceptance document + joint estimate of damage and payment of compensation

Information sessions

You can download the presentations from the various information sessions here:

Permit procedures

Permit procedure Public consultation Status
Declaration of Public Utility Aalter
Brugge
Damme
Evergem
Knokke-Heist
Lievegem
Maldegem
from 22/02/2024 to 23/03/2024
from 04/03/2024 to 02/04/2024
from 19/02/2024 to 20/03/2024
from 01/03/2024 to 30/03/2024
from 15/02/2024 to 16/03/2024
from 19/02/2024 to 19/03/2024
from 19/02/2024 to 20/03/2024
Transmission permit   Submitted on 4 Juli 2024
Environmental permit
for pipeline section 
Zeebrugge-Lievegem
Aalter
Brugge & Damme
Knokke-Heist
Lievegem
Maldegem
from 22/10/2024 to 20/11/2024
from 25/10/2024 to 23/11/2024
from 20/10/2024 to 18/11/2024
from 24/10/2024 to 20/11/2024
from 23/10/2024 to 21/11/2024
Environmental permit
for pipeline section
Lievegem-Evergem
Lievegem & Evergem from 28/10/2024 to 26/11/2024

Information sessions

You can download the presentations as part of the application for an environmental permit: