Incremental Capacity Process 2019

      Incremental Capacity Process 2019

        Incremental Capacity Process 2019

        The following diagram illustrates the key dates of the incremental process in 2019

         

        1 July 2019

         

        26 August 2019

           

        21 October 2019

        Yearly
        Capacity Auctions

        (first Monday of July)          

         

        Deadline submission of non-binding
        demand indications

        Start of work on DAR 2021

        (8 weeks after Yearly Capacity Auction start)

         

           

        Publication of DAR

        - On Fluxys website
        - On ENTSOG website

        (16 weeks after Yearly Capacity Auction start)

         

               

         

         

        Step 1 – Non-binding demand indications

        Parties interested in incremental capacity can submit non-binding demand indications at any time. However in the 2019 market demand assessment, Fluxys considered non-binding demand indications submitted no later than 26 August 2019 (cob). Non-binding demand indications received after this deadline will be considered in the next market demand assessment – in 2021.

        Non-binding demand indications can be submitted using the non-binding demand indications templates:

        Fluxys Belgium

        Download this form and send it to info.transport@fluxys.com.

        Fluxys TENP & Deutschland

        Download this form and send it to the TSO association FNB Gas.

        Interconnector UK

        Download this form and send it to consultation@interconnector.com


        Step 2 – Demand Assessment Reports (DAR)

        Fluxys
        Company
        IPs/Market Areas TSOs Document
        Fluxys Belgium ZTP-TTF Fluxys Belgium / GTS

        DAR ZTP-TTF

        Fluxys Belgium ZTPL-TTF Fluxys Belgium / GTS DAR ZPTL-TTF
        Fluxys Belgium ZTP-PEG Fluxys Belgium / GRTgaz DAR ZTP-PEG
        Fluxys Belgium ZTPL-PEG Fluxys Belgium / GRTgaz DAR ZTPL-PEG 
        Fluxys Belgium ZTP-THE
        Fluxys Belgium / Fluxys TENP, Gascade, OGE, Thyssengas
        DAR ZTP-THE
        Fluxys Belgium ZTP-IZT Fluxys Belgium / Interconnector
        DAR ZTP-INT

        Fluxys Deutschland

        THE-RU Fluxys Deutschland, GASCADE, Gasunie Deutschland, NEL Gastransport, ONTRAS Gastransport, OPAL Gastransport DAR THE-RU
        Fluxys Deutschland
        THE-N4G Fluxys Deutschland, GASCADE, ONTRAS Gastransport, Gasunie Deutschland, GRTGaz Deutschland, OGE / NET4gas

        DAR THE-N4G

        Fluxys TENP THE-ZTP Fluxys TENP, GASCADE, OGE, Thyssengas / Fluxys Belgium
        DAR THE-ZTP
        Fluxys TENP THE-Switzerland Fluxys TENP, Terranets BW, Bayernets, OGE
        DAR THE-Switzerland
        Fluxys TENP THE-TTF Fluxys TENP, GASCADE, Gasunie Deutschland, Thyssengas, Gastransport Nord, OGE / GTS
        DAR THE-TTF
        Interconnector IZT-ZTP Interconnector / Fluxys Belgium DAR INT-ZTP
        Interconnector IBT-NGG Interconnector / National Grid Gas DAR INT-NGG

        You can also consult the Demand Assessment Reports on the ENTSOG website